CASE Pilot Project

Lemminkäinen is a 100-year-old Finnish construction group. The company's market area encompasses Finland, Baltics and the entire world for the projects with the global customers.

Lemminkäinen and Tocoman have been developing BIM based quantity take-off and estimating since year 2007. One of our common projects is the new public transportation hub and a shopping center in Oulu, Finland. Tocoman provided software and consuting services, which enabled Lemminkäinen to utilize the BIM based estimating in the project. The BIM based methods saved a significant amount of time during the quantity take-off and estimating phases.

The exact content of our services and the final task durations are presented below. As you can see, major benefits can be achieved with relatively small effort, if you focus on the correct things.

TASKS HOURS
Project Management 12
- Preparing the meetings and workshops
12
Software Training 24
- Graphisoft ArchiCAD (done by Tocoman's local BIM partner)
16
- Tocoman iLink and Express 8
Actual Pilot Project 18
- Analyzing the building model and feedback to the designers
4
- Starting the BIM based quantity take-off and estimating (workshop)
8
- Hands-on support during the pilot project 6
Total
54 hrs

 

 
What Our Users Say

"Tocoman executes the projects and services in highly professional and client oriented manner.”

Miska Eriksson, Project Manager, Fira
 

"Tocoman did their consulting professionally and we were satisfied with the results."

Arto Kiviniemi, Research Professor, VTT
 